The traffic and crossing of vehicles on Hafaz square in Karaj lack the necessary safeties, particularly the entrance into the Hafez Square from Char-Hesar (the continuation of Chaloos- Karaj path) is so risky. In order to solve this problem and secure Char-Hesar crossing and Shahid Modarres Boulevard (Khalaj Abad), construction of a non-coplanar bridge over this boulevard was put on the agenda. Hafez Bridge, Technical buildings and the intersection of paths at the end of Modarres Boulevard and the intersection of line 4 of Hesar with Shahid Modarres Boulevard put into operation.

General specifications and project volumes:

  • Main employer: Karaj municipality
  • Employer Consultant: Gozar Rah consulting engineers
  • Construction contractor: Henza Co.
  • The weight of steel structure: 233 Tons
  • Steel structure contractor: Zhivar Sanat Kanyar Co.
  • Contract issues: Procurement,  construction, steel deck set up and bridge handrails installation
  • Contract closing date: 2013
  • Duration of contract: 3 months
  • Address: Hafez Square, Karaj

  • Location:
    Karaj, Alborz
  • Area:
    2
  • Start ِDate:
    Wednesday, 21 March 2012
  • Finish Date:
    Thursday, 21 March 2013
  • Project Type:
    Bridge